Installation or replacement of gas-using equipment

For the correct choice of gas-using equipment and its subsequent installation, consult a gas company or other company that has the appropriate permits. 

If you plan to use the services of installation (replacement) of gas-using equipment, make sure that the company you hire has a permit to perform high-risk work, gas-hazardous work! 

INSTALLATION OF GAS-USING EQUIPMENT 

The procedure and sequence of installation or replacement work is the same for any gas-using equipment. This can be a gas boiler, stove, gas convector or instantaneous water heater, heat generator, production furnaces and other installations. 

WHERE TO APPEAL AND WHAT TO DO? 

Advice on replacement or installation of gas-using equipment can be obtained: 

  • in the Contact Center of the PrJSC “Ternopilgaz” by phone:

(035) 2 519 904 – UKRTELECOM

(097) 0 519 904 – KYIVSTAR

(095) 0 519 904 – VODAFONE

WHAT DOCUMENTS ARE REQUIRED? 

  1. Statement from the consumer;
  2. Project for the object gasification;
  3. Copy of technical passport;
  4. Copy of the passport and identification code of the owner of the building for household consumers;
  5. Documents for the gas appliance (certificate of conformity and passport of the gas appliance manufacturer);
  6. Act of inspection of smoke and ventilation ducts (DVK Act) and scan with drawing of DVK structure.

PROJECT, PAYMENT FOR WORKS AND INSTALLATION 

Before installing gas-using equipment, it is necessary to obtain technical conditions from the district gas management department (when installing new equipment or replacing it with equipment of another type), make changes to the gas supply project of the facility (apartment, house, office, utility or industrial premises and etc.). The design department prepares technical documentation within the term stipulated by the agreement. 

Based on the calculation of the cost of construction and installation works, the consumer makes payment and then works on replacement or installation of gas-using equipment are performed. Terms of works performing are also regulated by the agreement.