Replacement of the outdoor-type gas pipeline near the town Berezhany, Ternopil District
The object of the Great Construction in 2021 in Ternopil Region is a highway M-12 Stryi - Ternopil - Kropyvnytskyi - Znamianka. Repair of a highway is carried out by the Turkish company Onur Group Ukraine and the service of motorways in Ternopil Region.
As a result of negotiations between Ternopilgaz and the motorway services, a decision was made on the expediency of simultaneous renovation of the gas pipeline under the highway in the town Berezhany, so as not to have to destroy a new road to replace gas networks that have been operating for more than 59 years.
It should be noted that the length of this low-pressure steel gas pipeline is 1650 meters, and it was built in 1962. Yard gas pipelines-inlets with a total length of 870 meters in the amount of 103 units also need to be replaced.
To date, specialists of Berezhany Department of Gas Management and the Capital Construction Department of Ternopilgaz main company have laid 1,480 meters of gas pipeline on Rohatynska Street and 59 yard entrances. There are 3 units of earthmoving equipment.
The works will start on July 15 and should be completed in the fall of this year.
The next object of reconstruction in Berezhany is a gas pipeline on Ternopilska Street. It is planned to replace 240 meters of gas networks and 6 yard entrances. We work for you!